Monolith Production Update June 2016

Monolith production is proceeding as expected. As of today all parts for Monolith Conical, but two (which should be completed by end of the week) have been machined and will undergo finishing next week. I expect all finishing will be done by end of month and then assembly and testing can begin. At this point the only delay that can be introduced is if finishers ruin parts and we have to remake them. It has happened once, but hopefully that was just glitch in the Matrix. 🙂

Monolith Flat parts production has also started, bases should be completed and finished next week and rest of parts should be machined by end of the month and then they are also off to finishing.

Here are couple of pics of raw parts as they came off of the CNC machines:

MonolithBases

 

MonolithShafts